Demolition works are being prepared on Saffron Gardens and Beardsley Gardens, with actual demolition starting next week.
Scheduled to start in the first week in July for Middle Furlong Gardens and the first week in August for Blackstone Walk and Manifold Gardens.
Saffron Gardens properties are fenced off and demolition is due to finish on 31st August.
Beardsley Gardens properties are also fenced off but demolition finishes earlier on 17th August.
Middle Furlong Gardens properties demolition starts on the 6th July and should also finish on 17th August.
Blackstone Walk and Manifold Gardens properties due for demolition – starts 3rd August and finishes on 19th October.
No doubt, the dates are subject to events.
Construction of new council housing meanwhile begins on 17th July, and the whole programme takes (from memory) 18 months.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s